PMI Risk Management Professional Practice Exam

Disable ads (and more) with a membership for a one time $4.99 payment

Study for the PMI Risk Management Professional Exam. Explore flashcards and multiple choice questions, each with detailed hints and explanations. Prepare to excel on your exam!

Practice this question and more.


A cost performance index (CPI) of 0.75 indicates what about the project?

  1. The project is behind schedule

  2. The project is under budget

  3. The project is over-budget to date

  4. The project is on track

The correct answer is: The project is over-budget to date

A cost performance index (CPI) is a measure used in project management to evaluate the cost efficiency and financial health of a project. It is calculated by dividing the earned value of work performed by the actual costs incurred. A CPI value less than 1, such as 0.75, indicates that the project is not delivering value commensurate with the expenditures made to date. In this case, a CPI of 0.75 means that for every dollar spent, the project is only earning 75 cents in value. This clearly signifies that the project is over-budget, as the actual costs are greater than the value of work accomplished. Therefore, this is why the choice indicating that the project is over-budget to date is the correct response. A CPI below 1 indicates the project is facing cost overruns, which is a critical insight for project managers to address issues and take corrective actions to bring the project back on track financially.