PMI Risk Management Professional Practice Exam

Disable ads (and more) with a membership for a one time $4.99 payment

Study for the PMI Risk Management Professional Exam. Explore flashcards and multiple choice questions, each with detailed hints and explanations. Prepare to excel on your exam!

Practice this question and more.


What is the risk rated high enough to require a proactive response based on a project's risk tolerance threshold of 17 percent?

  1. Probability—20 percent, impact—80 percent

  2. Probability—30 percent, impact—60 percent

  3. Probability—40 percent, impact—40 percent

  4. Probability—90 percent, impact—15 percent

The correct answer is: Probability—30 percent, impact—60 percent

To determine which risk requires a proactive response based on the specified project risk tolerance threshold of 17 percent, we can calculate the overall risk level using the formula: Overall Risk = Probability × Impact The risk levels for each option can be examined as follows: 1. For the first choice, if the probability is 20 percent and the impact is 80 percent, the overall risk is calculated as: 0.20 (Probability) × 0.80 (Impact) = 0.16 or 16 percent. 2. In the second choice, with a probability of 30 percent and impact of 60 percent: 0.30 × 0.60 = 0.18 or 18 percent. 3. The third choice, with a probability of 40 percent and an impact of 40 percent, gives: 0.40 × 0.40 = 0.16 or 16 percent. 4. Finally, for the fourth choice, with a probability of 90 percent and impact of 15 percent: 0.90 × 0.15 = 0.135 or 13.5 percent. Among these calculations, the second choice yields an overall risk level of 18